Metering package 2: MSATS and SLPs

The publication of the Final Report and Determination (Final Report) concludes the Rules consultation process conducted by the Australian Energy Market Operator (AEMO) to consider amendments to various Metering Procedures under the National Electricity Rules (NER), for the implementation of the five-minute settlement (5MS) and global settlement (GS) Rules, referred to as ‘Package 2’.  

For more information on the Metering Procedures Packages and associated consultation, see the 5MS Metering Procedures Packages factsheets (308 KB, pdf). 

Link to Consultation: Metering Procedure Changes (Package 2)

Status: Final determination published

Any queries should be directed to AEMO's Five-Minute Settlement email address: 5MS@aemo.com.au

  
Indicative Consultation Dates 
Publish consultation paper 20 May 2019      
Submissions due 24 June 2019 
Publish draft procedure and draft determination 5 August 2019 
Submissions due on Draft Report 2 September 2019 
Publish final procedure and final determination 30 September 2019 

**These documents were consulted on twice: firstly through package 1 for 5MS updates and secondly through package 2 for Global Settlement updates